NEW QUESTION # 190
Which is one of the three levels of plan in PRINCE2?
- A. Benefits Review Plan
- B. Team Plan
- C. Programme Plan
- D. Explanation:
QUESTIONNO:160
Which of the following statements about quality assurance and Project Assurance is true?
A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization - E. Project Brief
Answer: B
NEW QUESTION # 191
Which is a purpose of a project brief?
- A. To provide a description of the means and frequency of communication
- B. To act as a base document which enables the project board to assess progress
- C. To define how the achievement of the project's benefits can be measured
- D. To provide a sound basis for project initiation
Answer: D
Explanation:
http://www.prince2how2.com/2014/12/prince2-project-brief-template.html
NEW QUESTION # 192
Which two roles are linked by the Managing Product Delivery process?
- A. Corporate or programme management and Project Board
- B. Team Manager and external supplier
- C. Project Manager and Team Manager
- D. Project Board and Project Manager
Answer: C
NEW QUESTION # 193
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Change
- B. Progress
- C. Organization
- D. Quality
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-progress.php
NEW QUESTION # 194
Which is NOT a requirement of a Stage Plan?
- A. Approved and signed-off by Project Assurance
- B. Produced near to the end of the previous management stage
- C. Produced to an appropriate level of detail to enable day-to-day control
- D. Approved at the end of a management stage
Answer: A
NEW QUESTION # 195
Which product records any project outcomes perceived as negative by stakeholders?
- A. Business Case
- B. Project Product Description
- C. CommunicationManagement Strategy
- D. Project Plan
Answer: A
NEW QUESTION # 196
Which is a minimum requirement for applying the quality theme?
- A. To use user stories to inform the project product description
- B. To use external quality standards for quality control
- C. To use the prescribed approach to quality management
- D. To use lessons to inform quality planning
Answer: C
Explanation:
Reference http://prince2.wiki/Quality
NEW QUESTION # 197
Which is a minimum requirement for applying the quality theme?
- A. To use user stories to inform the project product description
- B. To use external quality standards for quality control
- C. To use the prescribed approach to quality management
- D. To use lessons to inform quality planning
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Quality
NEW QUESTION # 198
According to PRINCE2, why might there be more than one business case for a project?
- A. There may be more than one management stage in the project
- B. The project may be in a programme environment
- C. There may be more than one work package being delivered in the project
- D. The project may be in a commercial environment with a number of suppliers
Answer: D
Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/
NEW QUESTION # 199
Which describes risk probability?
- A. Probable effect on the project delivering its objectives
- B. A measure of the likelihood of the risk occurring
- C. Timeframe within which the risk may occur
- D. Level of risks which the project can tolerate before escalating to the Project Board
Answer: B
NEW QUESTION # 200
Which is a purpose of a Project Product Description?
- A. Define the quality required of the project's product
- B. Provide the initial project budget to be refined in the Business Case
- C. Form part of the Work Package for the project product
- D. Document the project mandate and gain approval for the project from the Project Board
Answer: A
NEW QUESTION # 201
Which of the following is the Business Case used for during the Managing a Stage Boundary process?
- A. Enable the Project Board to decide whether or not to authorize the project
- B. Justify the initiation of a project
- C. Justify the continuing viability of the project
- D. Enable the Project Board to decide whether or not to authorize project closure
Answer: C
NEW QUESTION # 202
According to PRINCE2, why might there be more than one business case for a project?
- A. There may be more than one management stage in the project
- B. The project may be in a programme environment
- C. There may be more than one work package being delivered in the project
- D. The project may be in a commercial environment with a number of suppliers
Answer: D
Explanation:
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/
NEW QUESTION # 203
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
- A. Specify the desired result
- B. Develop a project's products
- C. Ensure the technical integrity of a project
- D. Provide the resources and skills to deliver the desired result
Answer: A
NEW QUESTION # 204
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
- A. Continued business justification
- B. Manage by exception
- C. Manage by stages
- D. Learn from experience
Answer: B
Explanation:
Topic 3, Volume C
NEW QUESTION # 205
What process is used by the Project Board to respond to an Exception Report?
- A. Directing a Project
- B. Managing Product Delivery
- C. Controlling a Stage
- D. Managing a Stage Boundary
Answer: A
NEW QUESTION # 206
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?
- A. Project Board
- B. Corporate management
- C. Project Assurance
- D. Project Manager
Answer: D
NEW QUESTION # 207
Which statement describes the 'Implement' step within the recommended risk management procedure?
- A. Implement the responsibilities for risks defined in the Risk Management Strategy
- B. Identify the level of risks that can be tolerated by the project
- C. Take planned action to respond to a risk
- D. Assess the proximity of a risk
Answer: C
Explanation:
Section: Volume B
NEW QUESTION # 208
What is the minimum number of management stages required by PRINCE2?
- A. Four stages: to start, to initiate, to deliver and to close the project
- B. Three stages: to initiate, to deliver and to close the project
- C. One stage: to cover the whole project
- D. Two stages: to initiate and to deliver the project
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 209
......