NEW QUESTION # 190
Which is one of the three levels of plan in PRINCE2?

  • A. Benefits Review Plan
  • B. Team Plan
  • C. Programme Plan
  • D. Explanation:
    QUESTIONNO:160
    Which of the following statements about quality assurance and Project Assurance is true?
    A. Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
    B. Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
    C. Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
    D. Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
  • E. Project Brief

Answer: B


NEW QUESTION # 191
Which is a purpose of a project brief?

  • A. To provide a description of the means and frequency of communication
  • B. To act as a base document which enables the project board to assess progress
  • C. To define how the achievement of the project's benefits can be measured
  • D. To provide a sound basis for project initiation

Answer: D

Explanation:
http://www.prince2how2.com/2014/12/prince2-project-brief-template.html


NEW QUESTION # 192
Which two roles are linked by the Managing Product Delivery process?

  • A. Corporate or programme management and Project Board
  • B. Team Manager and external supplier
  • C. Project Manager and Team Manager
  • D. Project Board and Project Manager

Answer: C


NEW QUESTION # 193
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Change
  • B. Progress
  • C. Organization
  • D. Quality

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-progress.php


NEW QUESTION # 194
Which is NOT a requirement of a Stage Plan?

  • A. Approved and signed-off by Project Assurance
  • B. Produced near to the end of the previous management stage
  • C. Produced to an appropriate level of detail to enable day-to-day control
  • D. Approved at the end of a management stage

Answer: A


NEW QUESTION # 195
Which product records any project outcomes perceived as negative by stakeholders?

  • A. Business Case
  • B. Project Product Description
  • C. CommunicationManagement Strategy
  • D. Project Plan

Answer: A


NEW QUESTION # 196
Which is a minimum requirement for applying the quality theme?

  • A. To use user stories to inform the project product description
  • B. To use external quality standards for quality control
  • C. To use the prescribed approach to quality management
  • D. To use lessons to inform quality planning

Answer: C

Explanation:
Reference http://prince2.wiki/Quality


NEW QUESTION # 197
Which is a minimum requirement for applying the quality theme?

  • A. To use user stories to inform the project product description
  • B. To use external quality standards for quality control
  • C. To use the prescribed approach to quality management
  • D. To use lessons to inform quality planning

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Quality


NEW QUESTION # 198
According to PRINCE2, why might there be more than one business case for a project?

  • A. There may be more than one management stage in the project
  • B. The project may be in a programme environment
  • C. There may be more than one work package being delivered in the project
  • D. The project may be in a commercial environment with a number of suppliers

Answer: D

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/


NEW QUESTION # 199
Which describes risk probability?

  • A. Probable effect on the project delivering its objectives
  • B. A measure of the likelihood of the risk occurring
  • C. Timeframe within which the risk may occur
  • D. Level of risks which the project can tolerate before escalating to the Project Board

Answer: B


NEW QUESTION # 200
Which is a purpose of a Project Product Description?

  • A. Define the quality required of the project's product
  • B. Provide the initial project budget to be refined in the Business Case
  • C. Form part of the Work Package for the project product
  • D. Document the project mandate and gain approval for the project from the Project Board

Answer: A


NEW QUESTION # 201
Which of the following is the Business Case used for during the Managing a Stage Boundary process?

  • A. Enable the Project Board to decide whether or not to authorize the project
  • B. Justify the initiation of a project
  • C. Justify the continuing viability of the project
  • D. Enable the Project Board to decide whether or not to authorize project closure

Answer: C


NEW QUESTION # 202
According to PRINCE2, why might there be more than one business case for a project?

  • A. There may be more than one management stage in the project
  • B. The project may be in a programme environment
  • C. There may be more than one work package being delivered in the project
  • D. The project may be in a commercial environment with a number of suppliers

Answer: D

Explanation:
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/


NEW QUESTION # 203
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Specify the desired result
  • B. Develop a project's products
  • C. Ensure the technical integrity of a project
  • D. Provide the resources and skills to deliver the desired result

Answer: A


NEW QUESTION # 204
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

  • A. Continued business justification
  • B. Manage by exception
  • C. Manage by stages
  • D. Learn from experience

Answer: B

Explanation:
Topic 3, Volume C


NEW QUESTION # 205
What process is used by the Project Board to respond to an Exception Report?

  • A. Directing a Project
  • B. Managing Product Delivery
  • C. Controlling a Stage
  • D. Managing a Stage Boundary

Answer: A


NEW QUESTION # 206
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager report?

  • A. Project Board
  • B. Corporate management
  • C. Project Assurance
  • D. Project Manager

Answer: D


NEW QUESTION # 207
Which statement describes the 'Implement' step within the recommended risk management procedure?

  • A. Implement the responsibilities for risks defined in the Risk Management Strategy
  • B. Identify the level of risks that can be tolerated by the project
  • C. Take planned action to respond to a risk
  • D. Assess the proximity of a risk

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 208
What is the minimum number of management stages required by PRINCE2?

  • A. Four stages: to start, to initiate, to deliver and to close the project
  • B. Three stages: to initiate, to deliver and to close the project
  • C. One stage: to cover the whole project
  • D. Two stages: to initiate and to deliver the project

Answer: D