The PSPO-I certification exam is administered by Scrum.org, a leading global organization that provides training and certification for Scrum professionals. Scrum.org is committed to helping professionals enhance their knowledge and skills in Scrum and Agile methodologies, and the PSPO-I certification exam is one of the many certifications offered by the organization.
NEW QUESTION # 105
What are the implications of a Sprint length >4 weeks?
- A. Risk may increase.
- B. The Sprint Goal may become invalid.
- C. Quality will increase.
- D. Complexity may rise.
Answer: A,B,D
NEW QUESTION # 106
If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 107
Scrum's artifacts represent work or value.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 108
The Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 109
Which answer is correct about scaling Scrum (more than 1 team is working on the same product)?
- A. 1 product = 1 product backlog for each of the teams.
- B. 1 product = 1 product backlog for all teams.
- C. To work on 1 product with multiple teams is not allowed in Scrum.
Answer: B
NEW QUESTION # 110
When does a new Sprint start?
- A. When the Product Owner starts it.
- B. When the Scrum Master starts it.
- C. Immediately after the conclusion of the previous Sprint.
Answer: C
NEW QUESTION # 111
Following the Scrum theory, how should a group of 50 people be divided into multiple Scrum Teams?
- A. Create a matrix on skill level and form based on this groups.
- B. Decide this together with the program management.
- C. Scrum Teams are self-managing. That means that they should decide on their own how to form groups.
Answer: C
NEW QUESTION # 112
The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 113
The Sprint length can be 4 weeks.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 114
The Product Owner is responsible to define the Definition of Ready.
- A. False
- B. True
Answer: A
NEW QUESTION # 115
The Sprint Goal must be finalized prior to the end of Sprint Planning.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 116
Following Scrum, the Developers have to do the item estimation using Story Points.
- A. False
- B. True
Answer: A
NEW QUESTION # 117
Which statement about the size of the Development team ("Developers") is correct.
- A. Optimal Development Team size is small enough to remain nimble and large enough to complete significant work within a Sprint.
- B. The Optimal Development Team size is 6 +/- 2
- C. The optimal Development Team Size is 2-9 Developers.
Answer: A
NEW QUESTION # 118
Which statements describe best what happens in an organization if Scrum is introduced but the Scrum terminology is tailored to fit into the organizations environment?
- A. The organization will adapt the Scrum concepts faster due to the tailored approach.
- B. The change might not be obvious to every employee and some employees will not recognize it at all.
- C. The change might be not obvious to everyone and therefore little change will happen.
- D. The management may feel less enthusiastic about the new approach.
Answer: B,C,D
NEW QUESTION # 119
The Increment is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints.
- A. True
- B. False
Answer: A
NEW QUESTION # 120
The Sprint length can be 2 weeks.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 121
Besides the normal items, each Sprint Backlog contains at least one item about improving the way we work.
- A. False
- B. True
Answer: A
NEW QUESTION # 122
Product Backlog management can be done by a Scrum Master.
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 123
A good Scrum Team has at least one Release Sprint every year.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 124
What should you do, if Scrum Teams become too large?
- A. Nothing. The productivity and effectiveness will increase in bigger teams.
- B. Talk to the Program Manager about the situation.
- C. Consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product.
Answer: C
NEW QUESTION # 125
Where is an evolving environment reflected in Scrum?
- A. In the Product Backlog.
- B. In the Scrum Team salary.
- C. In the number of Product Owners assigned to the Team.
Answer: A
NEW QUESTION # 126
The Scrum Master is not important anymore if teams are self-managed.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION # 127
Which statements are true about Scrum artifacts?
- A. Scrum's artifacts represent work or revenue.
- B. Scrum artifacts are designed to maximize transparency of key information.
- C. Scrum's artifacts represent work or value.
Answer: B,C